Intersection work at Old Alabama/Old Alabama Connector starts in September

Posted:

Comment

ROSWELL, Ga. — The Roswell Department of Transportation (RDOT) will begin construction on a westbound right-turn lane along Old Alabama Road at the intersection of Old Alabama Road Connector in September.

The project also will add approximately 410 feet of sidewalk along Old Alabama Road between Old Alabama Road Connector and Roxburgh Drive. Construction is expected to be completed in October, weather permitting.

Travelers may experience delays with temporary lane closures; however, access through the area will be maintained.

The construction contract was awarded to Summit Construction at a cost of $120,984.85, funded by the city of Roswell.

For the more information, visit www.roswellgov.com/conezone.

RN-8-27