AAA Car Care Plus
appen grocery
Title Club
appen dec 2010 Duplicate

McGinnis Ferry bridge to be finished over summer


Horizontal beams just laid



New_Bridge_2_MQ
shadow
Workers extend an additional span of the McGinnis Ferry Road bridge over the Chattahoochee River. MATTHEW W. QUINN/Staff. (click for larger version)
April 19, 2012
JOHNS CREEK, Ga. — The McGinnis Ferry Road bridge over the Chattahoochee River is slated for completion over the summer.

Georgia Department of Transportation District 1 Communications Officer Teri Pope said construction on the bridge began Jan. 12, 2010. The horizontal beams were laid across the river over the weekend.

"That's a very exciting milestone event on a bridge project," she said.

Pope then described the process of building a bridge. The vertical caissons rise out of the river and the horizontal beams are laid on top to support the driving surface. Steel deck pans are laid between the beams to bind the structure together. After the pans are in place, work begins on the driving surface. Steel rebar is laid in a grid and concrete is poured; the rebar's purpose is to strengthen the concrete.

Once the concrete is poured, it will cure. Then GDOT will texture it and lay the stripes dividing the driving lanes from the shoulder and each other.

Pope explained that in addition to constructing the bridge, there is still work to be done on McGinnis Ferry Road itself. Only one open lane leaves Johns Creek, but two enter it.

"We've got to get traffic lined up with the new bridge," she said.

When it is finished, the road will have two lanes on either side divided by a grassy median, just like the rest of McGinnis Ferry Road.

Pope said GDOT is getting close, with an anticipated completion date over the summer. The official completion date is still being negotiated with contractor CW Matthews of Marietta.

Pope thanked the community for its patience, but warned drivers to slow down in the work zone to protect themselves and workers from injury. All fines for vehicular violations are doubled in work zones.

The combined project is 1.1 miles long and will cost $7.6 million. Like almost every other GDOT project, it is funded by federal and state gas tax collections. The federal gas tax funds 80 percent of the project, while the state gas tax funds 20 percent.

"First and foremost, I'm very excited that the bridge will be completed," said Mayor Mike Bodker.

He said this is the final piece of the puzzle in clearing up the eastbound congestion building up since McGinnis Ferry Road was widened.

"This will make driving between Gwinnett and Johns Creek much easier," he said.

list visuals View images.
Editor, Johns Creek Herald
printPrint
emailEmail Link
CommentFeedback
shareShare

Tags: Government & News & Crime

  1. report print email
    Bridge over the river Suwanee
    May 01, 2012 | 07:10 AM

    That'll really open up that stretch of road.

    Doncha just wonder why they started construction of the bridge AFTER the rest of the road was finished?

    That is a nice superhighway between JC & PTI, though I do wish they had the foresight to put in bike lanes as well.

    SafetyDave
    Alpharetta
  2. report print email
    Thunderdome
    May 07, 2012 | 03:54 PM

    "Only one open lane leaves Johns Creek, but two enter it."

    It's the Thunderdome area. Two lanes enter, one lane leaves.

    Cyan
    Arra
  3. report print email
    Bridge Leaving JC to PIB
    July 01, 2012 | 07:07 PM

    There was a perfectly fine bridge in place already that was taken down. There was no need to pay CW 8 million to replace this bridge and cause a traffice bottleneck night mare for 2 years. So much for tax payer money at work.

    Roger
    Johns Creek
  4. report print email
    Bridge to JC/PIB
    July 11, 2012 | 09:09 AM

    I have been driving this stretch of road for 10 years now. It is very frustrating to see the lack of progress and how long it takes the iron workers to do their part and then the concrete work. According to the web site last year, this was supposed to be finished by spring. I just don't understand why this is taking so long. If I see one more person leaning on a shovel I'll stop and say something to them. There should be incentives to finish ahead of schedule and penalties if not. Who negotiated this contract? Let's get this done. I'm tired of sitting in a 30 minute back-up each night heading home.

    Ron
    Lawrenceville
  5. report print email
    FINALLY!
    August 09, 2012 | 12:23 PM

    As of witnessing 10am today that **** bridge is finally done!!!

    I should throw a party!

    CHASE MOORE
    Dacula
READER COMMENTS Submission
When posting feedback please be respectful. Be nice. :
* required value
Your Name*

Town*

Email (not shown on website)*

Subject*

Comment*

Verification*
Identify the animal




Sandler Training
Coldwell Banker
Appen - NorthsideWoman promo
Appen - Free Publicity
ELECTRIC ANYTHING
We do any and all electric services including fans, surge protectors, new construction, rehab old electric. Licensed, bonded, realiable, local, and many references. $30 OFF WITH MENTION of this ad (minimum $200). Call 678-250-4470.
RECENT CLASSIFIEDS
Furniture

Wicker Bistro Table and Chairs

May 18, 2013 | 12:44 PM
Lloyd Flanders All-Weather »
TV/VCR/Video

TV 32 inch Sony Trinitron CRT

May 17, 2013 | 07:53 PM
Works great. Moving. $100 »
TV/VCR/Video

TV 60 inch Sony Grand WegaLCD projection

May 17, 2013 | 07:47 PM
Works great. Moving. $500 »

Beverage Depot
appen dec 2010